PREPARATIONS FOR THE RESTORATION OF SAINT SAVA CATHEDRAL ARE PROGRESSING STEADILY
The Department of Buildings and the Landmarks Commission have issued the permits for the removal of the decorative interior stone. This work is estimated to last between four and six weeks and will follow the erection of the scaffolding along the interior and exterior walls of the church. Once the removal of the stone is completed, the plan is to start the replacement of the current floor and commission the manufacturing of the roof beams.